- Open Source license compliance guide
- Objective: Provide concise, accessible information about the basic compliance requirements of common open source licenses across use cases.
- Status: First draft complete.
- Milestones:
- 1/18 Circulate to external experts and individual OSR participants
- 1/31 Complete review by external commentators and OSR participants
- 1/31 - 2/28 Resolve outstanding issues
- 2/28 Publish v0.1 as open source project
Open Source Readiness Assessment
- Objective: Evaluate and report on member readiness. Provide input into future OSR objectives.
- Status: Developing initial questionnaire.
- Milestones:
- 2/28 Finalize survey questions
- 3/30 Complete initial member surveys
- 5/31 Produce readiness scorecards and roadmaps for each participating FINOS member
- 7/31 Open assessment to wider participation
- 9/15 Publish industry-wide analysis
- OSR working group
- Objective: Provide timely presentations and discussions on readiness topics relevant to participants.
- Status: Still in initial stages of planning topics.
- Scheduled:
- 1/16 Kate Vershov: open source licenses - detailed overview (complete)
- 1/30 License compliance guide review & discussion
- 2/13 Open source compliance training discussion
- 3/13 Andrew Hall - overview of products for open source license compliance
- To be scheduled:
- Case Study: Innersource
- Case Study: Technical architecture of an open source review process
- Open Source Readiness Focus Groups
- Objective: intensive 4- to 8-hour open source readiness sessions with FINOS members in London and New York to work through practical open source readiness challenges.
- Status: Scheduling first (London) focus group
- Milestones (all dates approximate):
- 3/15 TBC New York focus group
- 5/2 London focus group
- 10/1 H2 - TBC New York focus group
- 12/1 H2 - TBC London focus group
- Open Source Strategy Roundtable - Capital Markets
- Objective: Identify shared development objectives to mutualize costs.
- Status: Identifying topic & participants for first roundtable.
- Milestones:
- 3/30 Roundtable complete
- 5/1 Report and recommendations published
- Innersource Pilot Roadmap
- Objective: Publish roadmap and resources for running an innersourcing pilot program within a bank.
- Status: Developing requirements.